| | Afamia
Beach Resort | | 2003 - 2006 | | | Afamia Beach Resort – Lattakia Syria;
construction of the Marina and
Breakwater using rocks all kind, pouring
of under water concrete, casting and
installation of concrete blocks, casting and
placing of Accropode blocks (12m3),
superstructure concrete, reinforced
concrete, under water excavation &
backfilling, dredging, protection wall
along the shoreline. |  | |
| | Ansaldo | | 1998 | | | Construction of Rock Breakwater to
protect power plant water outlet. |  | |
| | ATCL Kaslik
Yachting Club | | 1999 - 2000 | | | Construction of 165 m long fix Docks
with concrete columns base and Timber
walkway. |  | |
| | BUTEC | | 2004 - 2006 | | | Anfeh, Sewage treatment plant, BUTEC
construction of 700 l.m. underwater
pipeline up to 13 m of depth; The pipe
diameter is 30 cm and is GRP type. The
project includes underwater excavation,
dredging, backfilling, installation of
pipeline and fixing blocks system. |  | |
| | Chemicals of
Lebanon SAL | | 2004 - 2005 | | | Commercial port of Chemicals of
Lebanon SAL, Selaata, Batroun, repairing
the existing quay by using Accropode
blocks (16m3), under water excavation &
backfilling, pouring of under water
concrete. |  | |
| | Cimenterie National | | 1999 | | | Access Road in Cimenterie National – Chekka ; Excavating of 400,000 m3 of all
kinds plus the execution of the 2 km road
inside the company. |  | |
| | Cimenterie
National | | 2001 | | | Excavation of all kind about 120,000 m3 |  | |
| | Cimenterie
Nationale | | 1977 | | | Chekka Plant; construction of 2 steel building
for electro –filters (see brochure for more details) + air circulation system + steel
building used for Cement packaging
equipments with sand blasting & painting. |  | |
| | Cimenterie
Nationale S.A.L. | | 2001 - 2002 | | | Elongation and Restoration of existing quay
for Cimenterie Nationale commercial
Chekka port including: - underwater
concrete pouring to close existing caves
caused by erosion at quay walls.- dredging
of all kind material( rocks, sand,etc..)up to
15 meters below water surface level.-
casting & placingof 120 ton concrete
blocks using a crane barge at a depth of 12
meters below water surface level. |  | |
| | Consolidat
ed Steel of
Lebanon | | 1984 | | | Underwater Excavation of rocks (9000m3) to a depth of 4.5m below water surface level
Amchit. |  | |
|